04/05: The Louisiana Public Service Commission recommended that all industrial
customers with loads greater than five megawatts be given the choice to select
their power provider.
Source: Louisiana Public Service Commission
http://www.lpsc.org/default.asp
04/02: The Louisiana Public Service Commission (PSC) issued a restructuring
collaborative procedural schedule. The study groups had to submit their final
information to the commission no later than October 31, 2002 because the commission
planned to release its monitoring report on November 30, 2002. The report would
address transition cost estimates, the definition of a large industrial customer,
methods to encourage construction of capacity, and affiliate rules.
12/01: The Louisiana Public Service Commission issued two orders in regards
to analysis of competitive implications. The first order dealt with cogeneration
and plant construction. The second order declined to implement retail access
and the recommendations of the Staff’s report. The PSC would continue
to study restructuring and retail access as well as monitor its neighbors and
federal restructuring legislation.
07/01: The staff of the Louisiana PSC issued its final report, Final Response
of the Commission Staff to Comments on Proposed Competitive Transition Plan,
to the PSC. The report recommended some changes to the transition plan issued
in January including allowing open access to competitive service providers
to only large industrial customers with loads averaging 5 MW or more rather
than the original 2 MW load. Even though the PSC ruled two years ago that open
access was not in the State's best interest, a study of the issue continued
due to concerns about economic development. The report recommends another study
due in 2005 to determine if competition would benefit all classes of customers.
However, the PSC did not take any action on this latest report at their most
recent meeting, but may take it up in its September meeting.
01/01: The PSC issued a draft restructuring plan that would allow large industrial
customers retail choice starting in January 2003. Utilities would not be required
to divest their generation assets needed to serve their customer demands.
05/99: The PSC staff presented a report on restructuring recommending a slow
approach. The report raised skepticism on the benefits to residential consumers,
citing California's retail market where they said too few electricity suppliers
existed to have true competition. The report stated that Louisiana had lower
than average electric rates, and competition could increase prices, not lower
them. The report recommended no action toward retail competition be taken at
that time, but "reluctantly" submitted a draft restructuring plan
in case the PSC decided to go ahead. In Louisiana, the PSC could have ordered
retail competition without legislative action.
04/99: The PSC issued an order setting up a schedule through August 2000 to
study the issues: consumer education; stranded costs; regional planning and
reliability; market power; rate unbundling; functional unbundling; independent
system operators; and transition mechanisms.
03/99: The PSC issued an order stating that Commission "defers making
a public interest determination until such time that a Louisiana-specific transition
to competition plan has been fully developed. The Staff, outside consultants
and counsel are directed to recommend a plan for implementation of retail electric
generation competition for consideration by the Commission on or before January
1, 2001."
02/99: A draft report issued by the PSC advised not to go ahead with deregulation
due to concerns that residential consumers could experience higher prices.
The report also said that, however, if deregulation does go forward, it should
allow large industrials to shop for power while limiting rates for small consumers.
Louisiana consumers enjoyed rates that were less than the national average.
01/99: Entergy Gulf States and Entergy Louisiana submitted restructuring proposals
to the PSC. The PSC Chairman expected the PSC to rule that restructuring was
in the best interest of the State, but expected Louisiana to take a slow approach
to retail access.
08/98: The PSC conducted hearings on stranded costs. Participants included
Central Louisiana Electric Company, Enron, and Gulf State Utilities.
03/98: The PSC committee and the legislative committee met on March 16, 1998
to discuss the tax implications of deregulation.
12/97: The PSC voted to accept a staff report recommending further study on
issues surrounding electricity restructuring. The PSC was scheduled to develop
draft legislation for the 1999 session.
06/97: Resolution 150 created a study committee on electric power restructuring
with reports on various issues due in 1998.
05/95: The PSC opened Docket U-21453 on whether electric industry restructuring
was in the public interest.